Beginning on October 11th, the Town's contractor, Haluch Water Contracting, will be starting the Catalina St, Jenney St, and Fifth Ave ROW water main replacement project. The contractor plans on beginning with Catalina Drive and will then move to Jenney Street and will finish with Fifth Ave ROW. Construction is scheduled to take place Monday-Friday from 7:00 AM to 5:00 PM. During the project, traffic near the work area will be limited to one lane with an alternating traffic pattern. Police details will be present, however, we encourage all motorists, pedestrians, and cyclists to avoid the areas. Additional information will be posted as the project progresses including any scheduled interruptions in water service. This project is expected to be done in late November 2022.
We apologize in advance for any inconvenience this may cause. If you have any questions please contact the Water and Sewer Division at 508-841-8502 or dpwsupport@shrewsburyma.gov.