Important Update from the Water & Sewer Division - Water Main Work to Continue on Main Circle on 6/1

Water pump with text Shrewsbury Water Department and Established 1905 around pump

May 28, 2021 Water Main Replacement Project Update:  Contractor, Ricciardi Brothers Inc., has completed the water main replacement on Saybrook Road and will continue with Main Circle on Tuesday, June 1, 2021. They are also scheduled to replace the water main on School Street this season.

 Every effort is being made to minimize impacts to traffic, however delays can be expected and motorists, cyclists, and pedestrians are encouraged to seek alternate routes. Additional updates will be provided when water service will need to be interrupted for this project.

For additional information about this and other DPW projects please visit https://www.shrewsburyma.gov/1005/DPW---In-The-Works.  


We apologize in advance for any inconvenience this may cause.  If you have any questions please contact the Water and Sewer Division at 508-841-8502 or dpwsupport@shrewsburyma.gov. 


Facebook Twitter Email

Other News in Home

Solid Waste & Recycling Update

Posted on: July 30, 2021

Textile Recycling Program Update

Posted on: July 30, 2021

Maple & Main Night Road Work

Posted on: July 18, 2021
tick-borne-diseases-708x300.jpg

Tick Awareness

Posted on: April 6, 2021

Route 140 Roadwork

Posted on: June 10, 2021
2020 Annual Town Report

2020 Annual Town Report

Posted on: April 15, 2021

FY 2022 Fiscal Projection One

Posted on: March 8, 2021
Citizens Guide to the Budget Cover Image

Citizen's Guide to the Budget

Posted on: February 11, 2021

Project Bread FoodSource Hotline

Posted on: December 17, 2020

Route 140 Roadwork

Posted on: June 10, 2021

Selectmen Selections - June 2021

Posted on: June 30, 2021